Yelahanka Flyover Completion Delayed to May 2026, Three Years On
Quick Summary
- The construction of Bengaluru’s 1.8 km Yelahanka flyover, initiated in 2022 with an estimated cost of Rs 164 crore, aimed to create a signal-free route towards Doddaballapur Road.
- Initially slated for completion within 18 months, the project has missed several deadlines adn is now expected to be completed by May 2026.
- Causes for delay include lack of service road, restricted working hours (11 PM to 5:30 AM), land acquisition hurdles, and utility relocation challenges.
- Traffic bottlenecks have worsened beneath the incomplete flyover, especially near Seshadripuram College and NES Junction. Motorists and pedestrians face daily inconveniences with heightened congestion during weekends or holidays.
- Local residents express frustration over increased commuting times and safety concerns due to prolonged construction delays.
- Greater bengaluru Authority (GBA) claims that 65% of the work is completed; priorities have shifted toward ramp construction on Sandeep Unnikrishnan Road after completing most pillars and girders installation.
- Yelahanka MLA SR Vishwanath highlighted funding delays as a contributory factor but stated that issues are being resolved. Deadlines range from December 2025 proposed by civic officials to April/May 2026 according to broader estimates.