Yelahanka Flyover Completion Delayed to May 2026, Three Years On

IO_AdminUncategorized5 hours ago10 Views

Quick Summary

  • The construction of Bengaluru’s 1.8 km Yelahanka flyover, initiated in 2022 with an estimated cost of Rs 164 crore, aimed to create a signal-free route towards Doddaballapur Road.
  • Initially slated for completion within 18 months, the project has missed several deadlines adn is now expected to be completed by May 2026.
  • Causes for delay include lack of service road, restricted working hours (11 PM to 5:30 AM), land acquisition hurdles, and utility relocation challenges.
  • Traffic bottlenecks have worsened beneath the incomplete flyover, especially near Seshadripuram College and NES Junction. Motorists and pedestrians face daily inconveniences with heightened congestion during weekends or holidays.
  • Local residents express frustration over increased commuting times and safety concerns due to prolonged construction delays.
  • Greater bengaluru Authority (GBA) claims that 65% of the work is completed; priorities have shifted toward ramp construction on Sandeep Unnikrishnan Road after completing most pillars and girders installation.
  • Yelahanka MLA SR Vishwanath highlighted funding delays as a contributory factor but stated that issues are being resolved. Deadlines range from December 2025 proposed by civic officials to April/May 2026 according to broader estimates.

Image</a>“>  </p>
<hr>
<h3>Indian Opinion Analysis</h3>
<p>The Yelahanka flyover delay reflects both infrastructure planning gaps and execution setbacks commonly seen in urban development projects across India. While logistical challenges-such as land acquisition hurdles-are not unusual for large-scale projects like this one, the compounded effects on daily commuters highlight significant shortcomings in managing timelines effectively. Given Bengaluru’s rapid urbanisation trends, prolonged traffic inefficiencies near key routes exacerbate public dissatisfaction while impeding mobility essential for business operations.If GBA’s revised timeline holds true alongside MLA Vishwanath’s assurances regarding budgetary momentum returning on track, meeting expedited deadlines could ease long-term congestion issues; however consistent updates would maintain community trust during transitional disruptions further ensuring accountability.</p>
<p><strong>Read More:</strong> <a href=Times of India

0 Votes: 0 Upvotes, 0 Downvotes (0 Points)

Leave a reply

Recent Comments

No comments to show.

Stay Informed With the Latest & Most Important News

I consent to receive newsletter via email. For further information, please review our Privacy Policy

Advertisement

Loading Next Post...
Follow
Sign In/Sign Up Sidebar Search Trending 0 Cart
Popular Now
Loading

Signing-in 3 seconds...

Signing-up 3 seconds...

Cart
Cart updating

ShopYour cart is currently is empty. You could visit our shop and start shopping.